Celebrate 2025 with Discount Offer - Coupon code:

SAP C_TS412_2021 Exam Dumps

Certification Exams

Downloadable PDF versions

100% Confidential

Updated Regularly

Advanced Features

Number Of Questions: 110

$59.00

Exam Details

Exam Name:

SAP Certified Associate - SAP S/4HANA Project Systems

Exam Code:

C_TS412_2021

Total Questions in Exam:

110

Demo Questions

Q1. Material How can the system activate requirements (such as reservations or purchase requisitions)? Note: There are 2 correct answers to this question

A.Immediately, by saving the project

B. Automatically, using the requirement date and the replenishment lead time

C. Using a standard milestone activity

D. When releasing a network or an activity

Correct Answer: A, D

Q2. Your customer has created networks with internal activities and generated capacity requirements. Now, they want to analyze the capacity requirements of their project. Which report do you recommend?

A.Individual overview capacity requirements

B. Capacity load work center view

C. Extended capacity evaluation

D. Structure overview

Correct Answer: C

Q3. Which statements describe planned and actual revenue for WBS elements? Note: There are 2 correct answers to this question

A.Planned revenue requires a sales order assigned to a WBS element

B. Planned revenue can be transferred from a sales quotation

C. Actual revenue is posted via a billing plan assigned to a WBS element

D. Actual revenue is posted via a billing document created from a sales order

Correct Answer: A, D

Q4. Material Your customer uses Progress Tracking for network components and mantains dates of events manually. They need to implement scheduling of events. What is the requisites for implement scheduling of events?

A.Priority of events must be set.

B. Scheduling parameters for material scheduling must be set.

C. Events must be released manually.

D. Event scenarios must be defined.

Correct Answer: D

Q5. Resources How are capacity requirements determined?

A.Independent of scheduling and according to the capacity planner group.

B. Using scheduling and the capacity category.

C. Using the control key of an activity.

D. Using scheduling and distribution key.

Correct Answer: C

$59.00