Q1. A company has been using CI/CD. Its developers use Maven to handle build and deployment activities. What is the correct sequence of activities that takes place during the Maven build and deployment?

A.Initialize, validate, compute, test, package, verify, install, deploy

B. Validate, initialize, compile, package, test, install, verify, verify, deploy

C. Validate, initialize, compile, test package, verify, install, deploy

D. Validation, initialize, compile, test, package, install verify, deploy

Correct Answer: C

Q2. The Center for Enablement team published a common application as a reusable module to the central Nexus repository. How can the common application be included in all API implementations?

A.Download the common application from Naxus and copy it to the src/main/resources folder in the API

B. Copy the common application's source XML file and out it in a new flow file in the src/main/mule folder

C. Add a Maven dependency in the PCM file with multiple-plugin as

D. Add a Maven dependency in the POM file with jar as

Correct Answer: D

Q3. A developer has created the first version of an API designed for business partners to work commodity prices. What should developer do to allow more than one major version of the same API to be exposed by the implementation?

A.In Design Center, open the RAML and modify each operation to include the major version number

B. In Anypoint Studio, generate scaffolding from the RAML, and the modify the in the generated flows to include a parameter to replace the version number

C. In Design Center, open the RAML and modify baseUn to include a variable that indicates the version number

D. In Anypoint Studio, generate scaffolding from the RAML, and then modify the flow names generated by APIKit to include a variable with the major version number

Correct Answer: C

Q4. Which command is used to convert a JKS keystore to PKCS12?

A.Keytool-importkeystore --srckeystore keystore p12-srcstoretype PKCS12 --destkeystore keystore.jks --deststoretype JKS

B. Keytool-importkeystore --srckeystore keystore p12-srcstoretype JKS --destkeystore keystore.p12 --deststoretype PKCS12

C. Keytool-importkeystore --srckeystore keystore jks-srcstoretype JKS --destkeystore keystore.p13 --deststoretype PKCS12

D. Keytool-importkeystore --srckeystore keystore jks-srcstoretype PKCS12 --destkeystore keystore.p12 --deststoretype JKS

Correct Answer: B